Gas Project Tracker — November 20, 2026

All editions are on the Gas Project Tracker hub. This is the November 20, 2026 edition.

Gas Project Tracker — November 2026: Who Is Building U.S. Gas Plants

Project owners across the United States are still taking simple-cycle peakers and combined-cycle plants through public permitting and planning. This monthly tracker names the plants, the owners, the states, and the size of each project, then points to the filing or official page behind every row.

This is a research briefing, not an equipment list. HamidiTec does not publish models, prices, unit counts, or availability here, and this page does not describe any work HamidiTec is doing on any project. If you are building, expanding, or re-equipping a project, Request a Quote.

What changed since November 18

  • New approvals: The NC Utilities Commission issued a certificate on November 17 for Duke Energy’s 850 MW Buck combustion-turbine project in Rowan County. The Arizona Corporation Commission approved siting certificates the same day for SRP’s Marigold Energy Center in Pinal County, which includes up to 675 MW of simple-cycle gas generation.
  • Ohio approves two private data-center plants: On November 19 the Ohio Power Siting Board approved the 1,350 MW Fairfield Energy Center (Advanced Power, Fairfield County) and the 800 MW Ashville Energy Center (PowerConneX, Pickaway County). Neither plant will connect to the grid; each serves the data center next door.
  • Regulatory review complete: SWEPCO said on November 19–20 that commissions in Arkansas, Louisiana, and Texas have all approved its 450 MW Hallsville simple-cycle plant at the former Pirkey site in East Texas, which is under construction for late 2027.
  • Added to the tracker: Entergy Louisiana’s combined-cycle generation (about 5,278 MW) for Meta’s Richland Parish campus, sited in Richland and Pointe Coupee parishes. WWNO reported on November 19 that Entergy will seek Louisiana PSC approval in December.
  • Existing rows updated: Cameron Generation’s Louisiana permit filings now describe two plants totaling nearly 2.9 GW. SpaceX filed a second Texas air-permit application for the Starbase site on November 18, and Cameron County declined on November 17 to set a tax-abatement hearing. FirstEnergy says construction at Maidsville begins in 2027.
  • Correction: The Ameren West Alton sessions on November 18–19 were local public hearings. The evidentiary hearing is reported for April 2027.
  • Rechecked, no change: No final order yet on Peregrine (Idaho), Hickory Grove (Iowa), Sycamore Riverside’s utility acquisition (Indiana), or the Lume air permit (Georgia).
  • No new EIA or ERCOT data yet: EIA still lists November 24, 2026 as the release date for the October 2026 EIA-860M inventory. The latest ERCOT GIS report is still the October 2026 edition, posted November 2. PacifiCorp’s new Cluster 6 queue posting includes about 2.5 GW of gas requests, but owners were not identified, so none were added.

Earlier update (November 18, 2026)

  • Approved: The West Virginia PSC approved Mon Power and Potomac Edison’s 1,200 MW Maidsville Energy Center combined-cycle plant at the Fort Martin site on November 17, 2026.
  • New utility filings: Kentucky Power filed for a 769 MW combined-cycle plant at Big Sandy (KY PSC Case 2026-00324, November 13), and CIPCO’s 240 MW Hickory Grove peaker in Iowa went to hearing on November 17.
  • New announcements: Appalachian Power plans three West Virginia gas plants totaling about 3 GW by 2031, Invitium Energy (PPL / Blackstone Infrastructure) agreed nonbinding terms for about 2 GW anchored by two combined-cycle plants in Salem Township, Pennsylvania, and PSO broke ground on 450 MW at Northeastern Energy Campus in Oklahoma.
  • North Carolina resource plan: The NC Utilities Commission approved Duke Energy’s plan on November 16, including about 2,730 MW of new combined-cycle and about 1,111 MW of combustion-turbine capacity for 2030–2033; the supporting Davie-Davidson rezoning passed November 9.
  • Air permits for data-center generation: TCEQ issued permits for SpaceX’s 750 MW Starbase plant and a 149 MW Bastrop plant (November 16); Mississippi’s Permit Board upheld the roughly 1,200 MW Southaven permit (November 10); Ohio EPA issued a draft permit for the 500 MW Neo facility (November 12); Georgia EPD is reviewing Kindle Energy’s 990 MW Lume Energy Center; and Venture Global’s Cameron Generation filed with Louisiana DEQ.
  • New queue record (queue only): MISO fast-track (ERAS) requests for DOUBLEC Energy Center 3 and 4 in Crittenden County, Arkansas (750 MW combined cycle + 250 MW simple cycle). Owner not confirmed.
  • Existing rows rechecked: Mullin Creek #2 briefing is underway, with a decision requested by December 23. The Ameren West Alton hearings were set to begin November 18. No final order yet on Peregrine.
  • No new EIA or ERCOT data yet: The October 2026 EIA-860M inventory is due November 24, 2026. The latest ERCOT GIS report is still the October 2026 edition.

Earlier update (November 13, 2026)

  • Added five utility projects now in public filings: OG&E’s 755 MW Horseshoe Lake Unit 15 in Oklahoma, Ameren Missouri’s 2,100 MW West Alton combined-cycle plant, Evergy’s 440 MW Mullin Creek #2 peaker in Missouri, Georgia Power’s 1,500 MW Wansley combined-cycle plant, and PPL’s proposed 645 MW Kentucky combined-cycle plant.
  • Corrected two Wisconsin rows: the Wisconsin PSC granted conditional CPCNs to Foundry Ridge and Red Oak Ridge on October 15, 2026.
  • New ERCOT queue records (queue only): Ironwood Energy Center in Callahan County and a batch of seven roughly 991 MW combined-cycle requests from one interconnecting entity across Cameron, Leon, and Freestone counties.
  • No new EIA data yet: the October 2026 EIA-860M inventory is due November 24, 2026.

Methodology

This November 2026 first edition is a public-records refresh, current as of November 20, 2026 (America/New_York). Rows were built from:

  1. EIA-860M planned generators, September 2026 inventory, released October 23, 2026, from the Preliminary Monthly Electric Generator Inventory. The next release is November 24, 2026. This edition uses the Planned tab, filtered to “Natural Gas Fired Combustion Turbine” (shown as SC) and “Natural Gas Fired Combined Cycle” (shown as CC), including EIA status codes P, L, T, U, and V. Capacities are plant-level nameplate totals. EIA status codes used here:
  2. P — planned; regulatory approvals not initiated
  3. L — regulatory approvals pending; not under construction
  4. T — approvals received; not under construction
  5. U — under construction, 50 percent or less complete
  6. V — under construction, more than 50 percent complete
  7. State utility-commission and CPCN / siting dockets, including Wisconsin PSC, Idaho PUC, South Dakota PUC, Kentucky PSC, Missouri PSC, the Oklahoma Corporation Commission, the West Virginia PSC, the Iowa Utilities Commission, the NC Utilities Commission, the Ohio Power Siting Board, the Arizona Corporation Commission, and the Louisiana PSC, plus SWEPCO’s statement on its three-state approvals, plus official company project pages that accompany those filings.
  8. State air-permit pages, including the Pennsylvania DEP project page for the Montour CT Project, Missouri DNR’s White Cloud construction-application notice, South Carolina DES materials for Canadys, TCEQ approval as stated on Pacifico Energy’s GW Ranch page, and November 2026 actions by TCEQ, Georgia EPD, Ohio EPA, the Mississippi Permit Board, and Louisiana DEQ.
  9. ISO interconnection queues, principally the October 2026 ERCOT Generator Interconnection Status (GIS) report, whose official landing page is ERCOT Resource Adequacy, with project-level detail cited from Interconnection.fyi, plus new MISO Expedited Resource Addition Study (ERAS) records. Queue rows that have not also been confirmed in a permit, CPCN, or EIA planned-generator record are labeled queue only.

How to read the numbers. Size is the public plant-level figure, not a count of units and not an equipment list. Where EIA and an owner page differ, the table uses the EIA nameplate and the notes describe the owner figure. Several projects in active commission or permit review are not yet in the September 2026 EIA file; those rows are included from the docket or company page and marked as such. EIA status sometimes lags later public news, so a “planned” code is not, by itself, a finding that construction has not started.

This edition is a notable-project briefing, not a complete census. The September 2026 Planned tab covers many natural-gas plants. The tables below highlight verified owners and a short set of clearly flagged queue records.

Notable projects in public filings

These owners are identified in EIA-860M, a commission docket, an air-permit record, or the owner’s own project page.

In active commission or permit review

Developer / owner Project State Size (MW) Tech Status / stage Record What’s next
Invenergy / Foundry Ridge Energy Center, LLC Foundry Ridge Energy Center WI 324 SC CPCN granted with conditions by the Wisconsin PSC on October 15, 2026 (docket 9835-CE-100); EIA status P Wisconsin PSC case page, docket 9835-CE-100; Wisconsin PSC statement, October 15, 2026; EIA-860M Planned, September 2026, plant 70360 Final written order and state air permit. A separate utility application seeks authority to acquire the project.
NorthWestern Energy Hub City Energy Park SD 131 SC Energy conversion facility application filed October 2, 2026 (SD PUC EL26-031). Not listed in EIA-860M September 2026 Planned gas CT/CC. NorthWestern Energy, Hub City Energy Park; SD PUC EL26-031 Notice of Application Public input meeting November 23, 2026, in Aberdeen. Company timeline targets an EPC award in Q4 2026 and commercial operation in Q2 2030.
Idaho Power Peregrine Energy Center ID 430 SC CPCN still under review (Idaho PUC IPC-E-26-04); the commission deliberated on September 29, 2026, and no final order was found as of November 20, 2026. Elmore County local permits received spring 2026. Not listed in EIA-860M September 2026 Planned gas CT/CC. Idaho Power, Peregrine Energy Center; Idaho PUC IPC-E-26-04, Notice of Application, Order No. 36994 (April 6, 2026) Commission review continues. Company timeline: construction of Phase 1 in 2027–2028, Phase 1 in-service 2030, and evaluation of a possible Phase 2 in 2029.
Arizona Electric Power Cooperative / Mohave Electric Cooperative Mohave Energy Park AZ 242 SC EIA status L. Owner says necessary approvals to start site preparation are in hand and site preparation has begun. Mohave Energy Park project site (AEPCO / MEC); EIA-860M Planned, September 2026, plant 69773 Owner says construction of the generating units begins in late 2026, with the facility operational in 2028.
Pacifico Energy GW Ranch TX up to 7,650 SC/CC TCEQ air permit approved. Private-grid campus (not ERCOT-connected). Not listed in EIA-860M September 2026 Planned gas CT/CC. Pacifico Energy, GW Ranch Company targets first power in Q1 2027, 1 GW online in 2028, and 5+ GW of capacity in 2031, depending on customer needs.
East Kentucky Power Cooperative New Cooper Station generating unit KY 745 CC Public project brief; KY PSC case 2024-00370. Not listed in EIA-860M September 2026 Planned gas CT/CC. EKPC, New Cooper Station 745-MW generating unit brief; Kentucky PSC case 2024-00370 Commercial operation targeted for December 2030. Follow KY PSC case 2024-00370 for docket updates.
Talen Energy / Montour CT Project LLC Montour CT Project PA about 1,310 CC Air-quality application accepted; DEP project page last updated July 8, 2026, and still in permitting. Not listed in EIA-860M September 2026 Planned gas CT/CC. Pennsylvania DEP, Talen Montour CT Project (updated July 8, 2026) Construction is currently anticipated in 2028, with commercial operation expected in 2031, per the DEP project page.
Oklahoma Gas and Electric Company (OG&E) Horseshoe Lake Unit 15 OK 755 CC Preapproval application filed with the Oklahoma Corporation Commission (Case 2026-000094) on October 27, 2026. Not in EIA-860M September 2026. Oklahoma Energy Today, OCC Case 2026-000094; Hoodline, November 3, 2026 The commission has 180 days to act. Company targets service in late 2031, and a matching Arkansas filing is expected.
Union Electric Company (Ameren Missouri) West Alton combined-cycle facility (Sioux Energy Center site) MO 2,100 CC CCN application filed July 24, 2026 (Missouri PSC case EA-2026-0226), for three combined-cycle units; under Missouri PSC review. Local public hearings were held November 18 and 19, 2026. Not in EIA-860M September 2026. Missouri PSC order setting procedure, July 27, 2026; Sun Times News, PSC local public hearing notice Evidentiary hearing reported for April 2027; the company has asked for a decision in spring 2027 and targets 2031.
Evergy Missouri Metro Mullin Creek #2 MO 440 SC CCN application under Missouri PSC review (EA-2026-0154). Not in EIA-860M September 2026. Missouri PSC EA-2026-0154 application; Missouri PSC EA-2026-0154 procedural schedule Initial briefs were due November 16 and reply briefs are due November 24, 2026. The company asked for a final order by December 23, 2026, to issue notice to proceed in early 2027. Separate from Mullin Creek #1 below.
Georgia Power Company Plant Wansley Combined Cycle Units 10 and 11 GA 1,500 CC U.S. DOE completed its environmental review on November 6, 2026, for possible inclusion in a federal loan guarantee. Not in EIA-860M September 2026 Planned gas CT/CC. U.S. DOE, completion of environmental review, Wansley CC Full mobilization planned for January 2027; projected COD August 2029 (Unit 10) and December 2029 (Unit 11).
PPL Corporation (Kentucky utilities) Proposed Kentucky combined-cycle plant (site not disclosed) KY 645 CC Announced in the company capital plan; CPCN not yet filed. Utility Dive, November 9, 2026 CPCN filing anticipated in Q1 2027, after a data-center electric service agreement is signed. Company targets Q2 2032.
Monongahela Power / Potomac Edison (FirstEnergy) Maidsville Energy Center (Fort Martin site) WV 1,200 CC Approved. The West Virginia PSC granted approval to construct on November 17, 2026 (Case 26-0108-E-CN). Not in EIA-860M September 2026. WV PSC release, November 17, 2026; WV MetroNews, November 19, 2026 FirstEnergy says construction begins in 2027. The PSC requires 30 days’ notice before construction and a progress update in January 2027. Projected online in 2031.
Kentucky Power Company Big Sandy combined-cycle generation project KY 769 (760 per company release) CC CPCN and site compatibility application filed November 13, 2026 (KY PSC Case 2026-00324) to serve a planned data-center campus of up to 1 GW. Not in EIA-860M September 2026. KY PSC Case 2026-00324, application; Kentucky Lantern, November 18, 2026 Company says decisions could come as early as mid-2027. Expected commercial operation April 2031.
Central Iowa Power Cooperative (CIPCO) Hickory Grove Generating Station IA 240 SC Generating certificate application filed May 19, 2026; Iowa Utilities Commission evidentiary hearing began November 17, 2026. Iowa Utilities Commission, November 13, 2026 Hearing record, then a commission decision on the certificate.
Kindle Energy Lume Energy Center GA 990 SC Air construction permit application No. 30371 under Georgia EPD review (public comment closed November 6, 2026). Not in EIA-860M September 2026. Georgia EPD public advisory; EIP Oil & Gas Watch Georgia EPD permit decision. Developer expects operation in 2028.
Duke Energy Davie-Davidson Energy Complex (two combined-cycle units) NC Not stated per site CC The NC Utilities Commission approved Duke’s Carbon Plan / IRP on November 16, 2026, directing about 2,730 MW of new combined-cycle and about 1,111 MW of combustion-turbine generation for 2030–2033. Davidson County approved a rezoning for supporting fuel-storage facilities on November 9, 2026. NCUC press release, November 16, 2026; Duke Energy, Davie-Davidson Energy Complex; WXII, November 10, 2026 CPCN filing expected in 2027; construction projected 2029–2031. The 2,730 MW figure is the plan total, not a confirmed size for this site.
Duke Energy Carolinas Buck combustion turbine project (Buck Station) NC 850 SC Approved. The NC Utilities Commission issued the certificate of public convenience and necessity on November 17, 2026. Salisbury Post, November 17, 2026; Duke Energy, Buck project page A state air permit is still required before construction. Service targeted for 2030.
Salt River Project (SRP) Marigold Energy Center (thermal plant) AZ up to 675 SC Siting approved. The Arizona Corporation Commission approved the Certificates of Environmental Compatibility on November 17, 2026. Class I air permit application filed with Pinal County on September 11, 2026. The site also includes 600 MW of solar and 400 MW of storage. SRP, Marigold Energy Center; KJZZ, November 19, 2026 Pinal County air permit decision.
Entergy Louisiana Richland Units 1–4 and Pointe Coupee Units 1–3 (for Meta’s data-center campus) LA about 5,278 CC Certification application pending at the Louisiana PSC under its fast-track process. WWNO reported on November 19, 2026, that Entergy will seek approval in December. WWNO / Gulf States Newsroom, November 19, 2026; Entergy Louisiana application to the LPSC LPSC vote expected in December 2026. A November 9 lawsuit challenges the commission’s fast-track directive.

On-site generation for data centers and large loads (air permits)

These plants are being permitted to serve a specific large customer, often behind the meter. Most do not appear in EIA-860M yet.

Developer / owner Project State Size (MW) Tech Status / stage Record What’s next
SpaceX Starbase data-center power plant (off-grid) TX 750 SC TCEQ issued the electric-generating-unit standard permit on November 16, 2026. SpaceX filed a second air-permit application for the same site on November 18. Politico, November 17, 2026; MyRGV, November 17, 2026 TCEQ review of the second application. Cameron County voted 3–2 on November 17 not to set a tax-abatement hearing. A complaint alleging early construction is pending with TCEQ.
SpaceX Starlink factory on-site generation (Bastrop) TX 149 SC TCEQ issued standard permit registration 185366 on November 16, 2026. Construction not confirmed. Lost Pines Watch, updated November 17, 2026 Title V operating permit required before operation, per the TCEQ technical review.
MZX Tech LLC (SpaceXAI subsidiary) Southaven power plant MS about 1,200 SC Mississippi Permit Board upheld the March 2026 air permit on November 10, 2026, rejecting an appeal. Mississippi Today, November 12, 2026; MDEQ permit Watch for any further legal challenge.
Will-Power OH, LLC Neo Power Generation Facility OH 500 (plus 260 MW battery) SC Ohio EPA issued draft air permit P0140740 on November 12, 2026, for power supplied directly to an adjacent data center. OPSB case 26-0627-EL-BGN is pending. Ohio EPA notice, P0140740; OPSB case 26-0627-EL-BGN Public hearing December 17, 2026; comments close December 20, 2026.
Cameron Generation, LLC (Venture Global) Cameron Campus Data Center No. 2 generation LA about 2,900 (two plants) Gas Air permit applications received by Louisiana DEQ on October 15, 2026, for two dedicated plants, one beside the CP2 LNG terminal. The company describes the data center as potential and has not signed a customer. KPLC, November 13, 2026; EIP Oil & Gas Watch, November 19, 2026 LDEQ review. The company targets its first 250 MW of data-center power in late 2028.
Fairfield Energy Center, LLC (Advanced Power) Fairfield Energy Center OH up to 1,350 (plus 1,040 MW battery) SC Approved. The Ohio Power Siting Board granted the certificate on November 19, 2026 (case 26-0160-EL-BGN). Behind-the-meter supply to the adjacent Vantage Millersport data-center campus; not grid-connected. OPSB release, November 19, 2026; Signal Ohio, November 19, 2026 Remaining environmental permits. The developer estimates about three years of construction.
PowerConneX, Inc. (EdgeConneX) Ashville Energy Center OH 800 SC + engines Approved. The Ohio Power Siting Board granted the certificate on November 19, 2026 (case 26-196-EL-BGN). The plant mixes reciprocating engines with aeroderivative turbines and serves adjacent EdgeConneX data-center buildings. OPSB release, November 19, 2026; OPSB case 26-196-EL-BGN Opponents have said they plan to appeal. Construction on the site is reported to be under way.

Announced or under construction, not yet in EIA-860M

Developer / owner Project State Size (MW) Tech Status / stage Record What’s next
Appalachian Power Three new West Virginia gas plants (sites not yet announced) WV 3,000–3,300 Gas (type not disclosed) Announced November 12, 2026 by the West Virginia governor. WV Governor release, November 12, 2026; POWER magazine Site announcements and WV PSC filings. All capacity targeted to be online by 2031.
Invitium Energy (PPL / Blackstone Infrastructure joint venture) Salem Township data-center generation portfolio PA about 2,000 (portfolio, includes fuel cells and storage) CC Nonbinding key terms agreed with a data-center developer for two combined-cycle plants plus fuel cells and battery storage. No permits identified yet. PPL Q3 2026 Investor Update; Lehigh Valley Business Definitive agreement, then permitting. Gas plants targeted for 2032–2033.
Public Service Company of Oklahoma (PSO) Northeastern Energy Campus Units 5 and 6 OK 450 Gas Under construction. Ground broken November 9, 2026, after Oklahoma Corporation Commission approval earlier in 2026. PSO release, November 9, 2026 Commercial operation expected December 2028.
Southwestern Electric Power Company (SWEPCO) Hallsville Natural Gas Plant (former Pirkey site) TX 450 SC Under construction. SWEPCO said on November 19–20, 2026, that commissions in Arkansas, Louisiana, and Texas have all approved the project, completing regulatory review. Longview News-Journal, November 20, 2026; KLTV, November 19, 2026 Expected to begin serving customers in late 2027.

Other verified owners in the September 2026 EIA planned inventory

Developer / owner Project State Size (MW) Tech Status / stage Record What’s next
PowerSouth Energy Cooperative Lowman Energy Center AL 438 SC EIA status L; planned COD November 2029. EIA-860M Planned, September 2026, plant 56 Watch Alabama permitting and later EIA status changes.
Salt River Project Coolidge Generation Station addition AZ 297 SC EIA status U; planned COD July 2027. EIA-860M Planned, September 2026, plant 56948 Construction is underway, per EIA. Watch for a later-stage or in-service update.
Arizona Public Service Company Red Hawk AZ 392 SC EIA status U; planned COD October 2027. EIA-860M Planned, September 2026, plant 55455 Construction is underway, per EIA. Watch for a later-stage or in-service update.
City of Colorado Springs Horizon CO 480 SC EIA status P; planned COD July 2028. EIA-860M Planned, September 2026, plant 68705 Watch municipal / Colorado PUC or local permit updates and later EIA status changes.
Platte River Power Authority Rawhide Energy Station aeroderivative addition CO 223 SC EIA status P, planned COD March 2028. Owner says construction is planned to start in 2026 and lists energization in mid-2029. Platte River Power Authority, aeroderivative turbines; EIA-860M Planned, September 2026, plant 6761 Owner timeline: construction starting in 2026; energization mid-2029. Reconcile EIA vs owner COD in the next edition after the November 24, 2026 EIA-860M release.
Oglethorpe Power Corporation Talbot County Energy GA 262 SC EIA status P; planned COD January 2029. EIA-860M Planned, September 2026, plant 7916 Watch Georgia siting / company announcements and later EIA status changes.
Northern Indiana Public Service Company (NIPSCO) R.M. Schahfer generating addition IN 448.3 SC EIA status T; planned COD December 2027. EIA-860M Planned, September 2026, plant 6085 Near-term planned COD. Watch for construction updates and the next EIA-860M file.
Invenergy / Sycamore Riverside Energy, LLC Sycamore Riverside Energy IN 964 SC EIA status P; planned COD March 2029. EIA-860M Planned, September 2026, plant 70359 Watch Indiana siting / company announcements and later EIA status changes.
Union Electric Company (Ameren Missouri) Castle Bluff Energy Center MO 648 SC EIA status P; planned COD October 2027. EIA status can lag later public approvals. EIA-860M Planned, September 2026, plant 67576 Re-check the Missouri PSC docket and the next EIA-860M release. A near-term COD with a still-planned EIA code often means later public filings should be reviewed before treating the project as early-stage.
Evergy Missouri West Mullin Creek #1 Generating Station MO 489.7 SC EIA status T; planned COD January 2030. EIA-860M Planned, September 2026, plant 68296 Watch for a construction start or a status change in the next EIA-860M file.
White Cloud Generating, LLC White Cloud Generating MO 602.4 SC EIA status P. Missouri DNR construction application administratively complete July 2026. Missouri DNR, White Cloud Generating LLC application complete (July 2026); EIA-860M Planned, September 2026, plant 70485 Watch the Missouri DNR air-construction docket and later EIA status changes. Planned COD in the September 2026 EIA file is December 2028.
Tennessee Valley Authority New Caledonia MS 504 SC EIA status P; planned COD December 2028. EIA status can lag later public construction reports. EIA-860M Planned, September 2026, plant 69147 Re-check TVA project updates against the next EIA-860M release before treating the EIA ‘planned’ code as current field status.
Basin Electric Power Cooperative Bison Generation Station ND 1,518 CC EIA status L; planned CODs February 2029 and March 2030. EIA-860M Planned, September 2026, plant 69071 Watch North Dakota siting / company updates and later EIA status changes.
Lincoln Electric System Terry Bundy Generating Station addition NE 104 SC EIA status L; planned COD June 2029. EIA-860M Planned, September 2026, plant 7887 Watch LES procurement postings and later EIA status changes.
Omaha Public Power District Turtle Creek NE 264 SC EIA status T; planned COD August 2028. EIA-860M Planned, September 2026, plant 64547 Watch OPPD project updates and the next EIA-860M file.
Navajo Transitional Energy Company NTEC Gas Plant NM 1,089 SC EIA status L; planned COD June 2028. EIA-860M Planned, September 2026, plant 66478 Watch New Mexico permitting and later EIA status changes.
Santee Cooper / Dominion Energy Canadys Station NGCC SC 2,180* CC Draft air permit released by SCDES. Not listed in EIA-860M September 2026 Planned gas CT/CC. Santee Cooper, Generation Projects; South Carolina DES, Canadys Station Project Company says it remains on track to secure the final air permit and award the primary EPC contract by the end of 2026. Planned in-service date is 2Q 2033.
Santee Cooper Winyah Generating Station peaking addition SC 90–107 SC Engineering, procurement, and construction are underway, with site work in progress. Not listed as a planned gas CT in EIA-860M September 2026 (EIA lists only a petroleum-liquids unit at Winyah). Santee Cooper, Generation Projects Planned in-service date is 4Q 2027, per Santee Cooper.
CPV Basin Ranch CPV Basin Ranch Energy Center TX 1,445 CC EIA status U; planned COD February 2029. Also present in the October 2026 ERCOT GIS report. EIA-860M Planned, September 2026, plant 69566; ERCOT Resource Adequacy / monthly GIS report landing page Construction is underway, per EIA. Watch later EIA and ERCOT GIS updates.
Golden Spread Electric Cooperative Elk Station TX 199.8 SC EIA status U; planned COD March 2027. EIA-860M Planned, September 2026, plant 58835 Construction is underway, per EIA. Watch for a later-stage or in-service update.
Arkansas Electric Cooperative Corporation Naples Power Plant TX 900 SC EIA status P; planned COD December 2028. EIA-860M Planned, September 2026, plant 68273 Watch TCEQ and later EIA status changes.
Fermi America Project Matador Gas Plant (PMG) TX 11,679.3 SC/CC EIA mixed P/T/U across a large multi-unit buildout. Planned CODs range from June 2027 to December 2030. EIA-860M Planned, September 2026, plant 69799 Large, phased campus. Watch later EIA-860M vintages and Texas air-permit updates for the next phases.
Virginia Electric and Power Company (Dominion Energy) Chesterfield VA 1,000 SC EIA status L; planned COD June 2029. EIA-860M Planned, September 2026, plant 3797 Watch Virginia SCC / company project updates and the November 24, 2026 EIA-860M file for status changes.
Invenergy / Red Oak Ridge Energy Center, LLC Red Oak Ridge Energy Center WI 1,210 SC CPCN granted with conditions by the Wisconsin PSC on October 15, 2026; EIA mixed L/P; planned COD December 2029. EIA-860M Planned, September 2026, plant 70453; Wisconsin PSC statement, October 15, 2026 Final written order and air permitting; watch the next EIA-860M for a status change.
Wisconsin Electric Power Company South Oak Creek WI 1,181.5 SC EIA status L; planned COD February 2028. EIA-860M Planned, September 2026, plant 4041 Watch Wisconsin PSC filings and later EIA status changes.
Black Hills Cheyenne Prairie Generating Station addition WY 120 SC EIA status P; planned COD December 2028. EIA-860M Planned, September 2026, plant 57703 Watch Wyoming siting / company updates and later EIA status changes.

* Canadys is a joint Santee Cooper / Dominion Energy plant. Santee Cooper states that 1,090 MW is its portion of the project. Public IRP materials describe a plant of about 2,180 MW.

Withdrawn or stale filings

EIA-860M can continue to show a plant after a siting case has been pulled. The row below is included so later editions can track a possible refile.

Developer / owner Project State Size (MW) Tech Status / stage Record What’s next
Western Minnesota Municipal Power Agency / Missouri River Energy Services Toronto Power Plant SD 145.2 SC WITHDRAWN. SD PUC granted withdrawal of the application without prejudice and closed EL25-028 on November 9, 2026. EIA-860M September 2026 still shows status L. SD PUC EL25-028 (docket closed November 9, 2026; order granting withdrawal without prejudice); EIA-860M Planned, September 2026, plant 69102 Watch for a possible refile at a new location. Do not treat the September 2026 EIA row as an active siting case.

Queue-only records (not yet confirmed in a permit or CPCN)

An interconnection request is an early signal, not proof that a plant will be built. Many ERCOT gas requests are still screening-level or are filed by project LLCs. The ERCOT rows below were active in the October 2026 ERCOT GIS report; the Arkansas row is a MISO ERAS record. They have not been confirmed in this edition with an air permit, a CPCN, or an EIA planned-generator record. LCRA is a known public-power owner; that row is still flagged as a queue record until a permit or commission docket is confirmed.

Developer / owner Project State Size (MW) Tech Status / stage Record What’s next
Energy Forge One LLC Kilby1 Part 6 Large Block Combined Cycle TX 1,056 CC QUEUE ONLY. Active in the ERCOT interconnection queue. No IA date listed on the Interconnection.fyi project page. No air-permit or PUC confirmation in this edition. Interconnection.fyi, ERCOT 29INR0199; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Revisit when a permit, CPCN, or interconnection agreement appears.
Trailblazer Infrastructure LLC Trailblazer Natural Gas Generation Plant TX 1,026 Gas QUEUE ONLY. Active in the ERCOT interconnection queue. The project page does not specify simple-cycle vs combined-cycle. No air-permit or PUC confirmation in this edition. Proposed COD of December 2027 is aggressive if permits are not already in hand. Interconnection.fyi, ERCOT 27INR0575; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Triangulate with a permit or CPCN before treating it as a live build.
Liberty Data Center I, LLC Liberty Thermal Energy Center TX 1,400 Gas QUEUE ONLY. Active in the ERCOT interconnection queue. Long-dated proposed COD (July 1, 2032). No air-permit or PUC confirmation in this edition. Interconnection.fyi, ERCOT 33INR0006; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Confirm ownership, permits, and that the interconnecting entity would own and operate the generation.
Bullock Data Center, LLC Bullock Gas TX 1,400 Gas QUEUE ONLY. Active in the ERCOT interconnection queue. Long-dated proposed COD (July 1, 2032). No air-permit or PUC confirmation in this edition. Interconnection.fyi, ERCOT 33INR0005; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Confirm ownership, permits, and that the interconnecting entity would own and operate the generation.
LCRA Sim Gideon Combined Cycle TX 880 CC QUEUE RECORD, known public-power owner. Active in the ERCOT interconnection queue. No separate CPCN or air-permit confirmation in this edition. Not listed in EIA-860M September 2026 Planned gas CT/CC. Interconnection.fyi, ERCOT 30INR0051; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) A known owner, but still a queue record until a permit or CPCN is confirmed. Proposed COD December 15, 2030.
Ironwood Energy Center LLC Ironwood Energy Center I and II TX 2,227 (1,485 + 742) CC QUEUE ONLY. New in the October 2026 ERCOT GIS report (30INR0106, 30INR0107); studies started, no interconnection agreement. Parent company not confirmed. ERCOT GIS October 2026 via SubstationScout; ERCOT Resource Adequacy Watch for a TCEQ air-permit application or a named parent. Target COD July 2032.
Black Mountain Energy Storage II (interconnecting entity) Rattler CC Energy Center I–III (Cameron), Great Rock Energy Center II–III (Leon), BM Freestone Energy Center II–III (Freestone) TX about 6,934 (seven requests of about 991) CC QUEUE ONLY. Seven new combined-cycle requests in the October 2026 ERCOT GIS report (29INR0410, 0415–0420); studies started, no interconnection agreement. ERCOT GIS October 2026 via SubstationScout; Parcel & Grid ERCOT Queue Brief, October 2026 A batch of identical requests often signals site screening. Treat as speculative until permits appear.
Doublec Energy (interconnecting entity; owner unconfirmed) DOUBLEC Energy Center 3 and 4 AR 1,000 (750 + 250) CC + SC QUEUE ONLY. New MISO Expedited Resource Addition Study (ERAS) requests (E0072, E0071) to serve resource adequacy for new large loads; Entergy Arkansas is the transmission owner. Interconnection.fyi, MISO E0072; Interconnection.fyi queue update, November 5, 2026 Watch for an Arkansas PSC filing or air permit naming the owner. Proposed completion February 2029.

What this edition shows

  • Several mid-size simple-cycle projects are moving through approvals or early construction planning: Foundry Ridge in Wisconsin now has a conditional CPCN, while Hub City in South Dakota, Peregrine in Idaho, and Mullin Creek #2 in Missouri remain in commission review, and Mohave Energy Park in Arizona has begun site preparation.
  • Large regulated combined-cycle plants are back in utility filings, led by Ameren Missouri at West Alton, Georgia Power at Wansley, and OG&E at Horseshoe Lake.
  • Combined-cycle additions tied to existing stations — Montour in Pennsylvania and Cooper Station in Kentucky — are moving through air permitting or public project planning, even though they are not yet in the September 2026 EIA planned file.
  • Private-grid and data-center-related generation is visible both in permitted form (GW Ranch in Pecos County, Texas) and in still-unconfirmed queue records in Hill County.
  • At least one otherwise well-documented mid-size municipal project, Toronto Power Plant in South Dakota, has had its siting application withdrawn. It remains in the September 2026 EIA file and should be watched for a refile, not treated as an active case.
  • Generation built for one large offtaker is now a category of its own. Kentucky Power’s Big Sandy filing and the Invitium terms in Pennsylvania are utility-led, while the Texas, Mississippi, Ohio, and Louisiana permits are for on-site plants that serve data centers directly.
  • West Virginia moved from announcements to approvals: one 1,200 MW combined-cycle plant is now approved, and about 3 GW more was announced on November 12.
  • Private generation for data centers is now getting state siting approval, not just air permits. Ohio’s siting board approved Fairfield and Ashville on the same day, about 2.15 GW combined, and neither plant will connect to the public grid.
  • The next EIA-860M release, on November 24, 2026, is the first place to look for status changes and for plants that have not yet appeared in the federal inventory.

If you are building a plant

HamidiTec works with end users and project owners — utilities, developers, cooperatives, EPCs, and the funds that directly back them. We fulfill new and refurbished gas turbines and related power-generation equipment, bought direct from the vendor or manufacturer. We do not publish an equipment list on this site.

If you have a project in permitting, procurement, or early engineering, Request a Quote.

Compiled by HamidiTec LLC for the November 2026 Gas Project Tracker. Figures are taken from the public filings linked above and are current as of November 20, 2026 (America/New_York). This post will be revised as new EIA, commission, permit, and queue records are published.