U.S. Gas Power Plant Project Tracker: November 2026

gas turbine power plant

A newer edition is available

Project owners across the United States are still taking simple-cycle peakers and combined-cycle plants through public permitting and planning. This monthly tracker names the plants, the owners, the states, and the size of each project, then points to the filing or official page behind every row.

This is a research briefing, not an inventory list. HamidiTec does not publish equipment availability, prices, or delivery dates here. If you are an owner, developer, utility, EPC, or a fund that directly backs a project, send me your project and I will match it to equipment.

Methodology

This November 2026 first edition is a public-records refresh, current as of November 12, 2026 (America/New_York). Rows were built from:

  1. EIA-860M planned generators, September 2026 inventory, released October 23, 2026, from the Preliminary Monthly Electric Generator Inventory. The next release is November 24, 2026. This edition uses the Planned tab, filtered to “Natural Gas Fired Combustion Turbine” (shown as SC) and “Natural Gas Fired Combined Cycle” (shown as CC), including EIA status codes P, L, T, U, and V. Capacities are plant-level nameplate totals. EIA status codes used here:
  2. P — planned; regulatory approvals not initiated
  3. L — regulatory approvals pending; not under construction
  4. T — approvals received; not under construction
  5. U — under construction, 50 percent or less complete
  6. V — under construction, more than 50 percent complete
  7. State utility-commission and CPCN / siting dockets, including Wisconsin PSC, Idaho PUC, South Dakota PUC, and Kentucky PSC, plus official company project pages that accompany those filings.
  8. State air-permit pages, including the Pennsylvania DEP project page for the Montour CT Project, Missouri DNR’s White Cloud construction-application notice, South Carolina DES materials for Canadys, and TCEQ approval as stated on Pacifico Energy’s GW Ranch page.
  9. ISO interconnection queues, principally the October 2026 ERCOT Generator Interconnection Status (GIS) report, whose official landing page is ERCOT Resource Adequacy, with project-level detail cited from Interconnection.fyi. Queue rows that have not also been confirmed in a permit, CPCN, or EIA planned-generator record are labeled queue only.

How to read the numbers. Size is the public plant-level figure, not a count of units and not an equipment list. Where EIA and an owner page differ, the table uses the EIA nameplate and the notes describe the owner figure. Several projects in active commission or permit review are not yet in the September 2026 EIA file; those rows are included from the docket or company page and marked as such. EIA status sometimes lags later public news, so a “planned” code is not, by itself, a finding that construction has not started.

This edition is a notable-project briefing, not a complete census. The September 2026 Planned tab alone lists 192 natural-gas combustion-turbine units and 236 natural-gas combined-cycle units, which roll up to 91 plants. The tables below highlight verified owners and a short set of clearly flagged queue records.

Notable projects in public filings

These owners are identified in EIA-860M, a commission docket, an air-permit record, or the owner’s own project page.

In active commission or permit review

Developer / owner Project State Size (MW) Tech Status / stage Source What’s next
Invenergy / Foundry Ridge Energy Center, LLC Foundry Ridge Energy Center WI 324 SC CPCN under review (WI PSC 9835-CE-100); EIA status P Wisconsin PSC case page, docket 9835-CE-100; EIA-860M Planned, September 2026, plant 70360 Commission review continues. If approved, the applicant has targeted construction beginning September 2026 and completion in March 2028.
NorthWestern Energy Hub City Energy Park SD 131 SC Energy conversion facility application filed October 2, 2026 (SD PUC EL26-031). Not listed in EIA-860M September 2026 Planned gas CT/CC. NorthWestern Energy, Hub City Energy Park; SD PUC EL26-031 Notice of Application Public input meeting November 23, 2026, in Aberdeen. Company timeline targets an EPC award in Q4 2026 and commercial operation in Q2 2030.
Idaho Power Peregrine Energy Center ID 430 SC CPCN still under review (Idaho PUC IPC-E-26-04). Elmore County local permits received spring 2026. Not listed in EIA-860M September 2026 Planned gas CT/CC. Idaho Power, Peregrine Energy Center; Idaho PUC IPC-E-26-04, Notice of Application, Order No. 36994 (April 6, 2026) Commission review continues. Company timeline: construction of Phase 1 in 2027–2028, Phase 1 in-service 2030, and evaluation of a possible Phase 2 in 2029.
Arizona Electric Power Cooperative / Mohave Electric Cooperative Mohave Energy Park AZ 242 SC EIA status L. Owner says necessary approvals to start site preparation are in hand and site preparation has begun. Mohave Energy Park project site (AEPCO / MEC); EIA-860M Planned, September 2026, plant 69773 Owner says construction of the generating units begins in late 2026, with the facility operational in 2028.
Pacifico Energy GW Ranch TX up to 7,650 SC/CC TCEQ air permit approved. Private-grid campus (not ERCOT-connected). Not listed in EIA-860M September 2026 Planned gas CT/CC. Pacifico Energy, GW Ranch Company targets first power in Q1 2027, 1 GW online in 2028, and 5+ GW of capacity in 2031, depending on customer needs.
East Kentucky Power Cooperative New Cooper Station generating unit KY 745 CC Public project brief; KY PSC case 2024-00370. Not listed in EIA-860M September 2026 Planned gas CT/CC. EKPC, New Cooper Station 745-MW generating unit brief; Kentucky PSC case 2024-00370 Commercial operation targeted for December 2030. Follow KY PSC case 2024-00370 for docket updates.
Talen Energy / Montour CT Project LLC Montour CT Project PA about 1,310 CC Air-quality application accepted; DEP project page last updated July 8, 2026, and still in permitting. Not listed in EIA-860M September 2026 Planned gas CT/CC. Pennsylvania DEP, Talen Montour CT Project (updated July 8, 2026) Construction is currently anticipated in 2028, with commercial operation expected in 2031, per the DEP project page.

Other verified owners in the September 2026 EIA planned inventory

Developer / owner Project State Size (MW) Tech Status / stage Source What’s next
PowerSouth Energy Cooperative Lowman Energy Center AL 438 SC EIA status L; planned COD November 2029. EIA-860M Planned, September 2026, plant 56 Watch Alabama permitting and later EIA status changes.
Salt River Project Coolidge Generation Station addition AZ 297 SC EIA status U; planned COD July 2027. EIA-860M Planned, September 2026, plant 56948 Construction is underway, per EIA. Watch for a later-stage or in-service update.
Arizona Public Service Company Red Hawk AZ 392 SC EIA status U; planned COD October 2027. EIA-860M Planned, September 2026, plant 55455 Construction is underway, per EIA. Watch for a later-stage or in-service update.
City of Colorado Springs Horizon CO 480 SC EIA status P; planned COD July 2028. EIA-860M Planned, September 2026, plant 68705 Watch municipal / Colorado PUC or local permit updates and later EIA status changes.
Platte River Power Authority Rawhide Energy Station aeroderivative addition CO 223 SC EIA status P, planned COD March 2028. Owner says construction is planned to start in 2026 and lists energization in mid-2029. Platte River Power Authority, aeroderivative turbines; EIA-860M Planned, September 2026, plant 6761 Owner timeline: construction starting in 2026; energization mid-2029. Reconcile EIA vs owner COD in the next edition after the November 24, 2026 EIA-860M release.
Oglethorpe Power Corporation Talbot County Energy GA 262 SC EIA status P; planned COD January 2029. EIA-860M Planned, September 2026, plant 7916 Watch Georgia siting / company announcements and later EIA status changes.
Northern Indiana Public Service Company (NIPSCO) R.M. Schahfer generating addition IN 448.3 SC EIA status T; planned COD December 2027. EIA-860M Planned, September 2026, plant 6085 Near-term planned COD. Watch for construction updates and the next EIA-860M file.
Invenergy / Sycamore Riverside Energy, LLC Sycamore Riverside Energy IN 964 SC EIA status P; planned COD March 2029. EIA-860M Planned, September 2026, plant 70359 Watch Indiana siting / company announcements and later EIA status changes.
Union Electric Company (Ameren Missouri) Castle Bluff Energy Center MO 648 SC EIA status P; planned COD October 2027. EIA status can lag later public approvals. EIA-860M Planned, September 2026, plant 67576 Re-check the Missouri PSC docket and the next EIA-860M release. A near-term COD with a still-planned EIA code often means later public filings should be reviewed before treating the project as early-stage.
Evergy Missouri West Mullin Creek #1 Generating Station MO 489.7 SC EIA status T; planned COD January 2030. EIA-860M Planned, September 2026, plant 68296 Watch for a construction start or a status change in the next EIA-860M file.
White Cloud Generating, LLC White Cloud Generating MO 602.4 SC EIA status P. Missouri DNR construction application administratively complete July 2026. Missouri DNR, White Cloud Generating LLC application complete (July 2026); EIA-860M Planned, September 2026, plant 70485 Watch the Missouri DNR air-construction docket and later EIA status changes. Planned COD in the September 2026 EIA file is December 2028.
Tennessee Valley Authority New Caledonia MS 504 SC EIA status P; planned COD December 2028. EIA status can lag later public construction reports. EIA-860M Planned, September 2026, plant 69147 Re-check TVA project updates against the next EIA-860M release before treating the EIA ‘planned’ code as current field status.
Basin Electric Power Cooperative Bison Generation Station ND 1,518 CC EIA status L; planned CODs February 2029 and March 2030. EIA-860M Planned, September 2026, plant 69071 Watch North Dakota siting / company updates and later EIA status changes.
Lincoln Electric System Terry Bundy Generating Station addition NE 104 SC EIA status L; planned COD June 2029. EIA-860M Planned, September 2026, plant 7887 Watch LES procurement postings and later EIA status changes.
Omaha Public Power District Turtle Creek NE 264 SC EIA status T; planned COD August 2028. EIA-860M Planned, September 2026, plant 64547 Watch OPPD project updates and the next EIA-860M file.
Navajo Transitional Energy Company NTEC Gas Plant NM 1,089 SC EIA status L; planned COD June 2028. EIA-860M Planned, September 2026, plant 66478 Watch New Mexico permitting and later EIA status changes.
Santee Cooper / Dominion Energy Canadys Station NGCC SC 2,180* CC Draft air permit released by SCDES. Not listed in EIA-860M September 2026 Planned gas CT/CC. Santee Cooper, Generation Projects; South Carolina DES, Canadys Station Project Company says it remains on track to secure the final air permit and award the primary EPC contract by the end of 2026. Planned in-service date is 2Q 2033.
Santee Cooper Winyah Generating Station peaking addition SC 90–107 SC Engineering, procurement, and construction are underway, with site work in progress. Not listed as a planned gas CT in EIA-860M September 2026 (EIA lists only a petroleum-liquids unit at Winyah). Santee Cooper, Generation Projects Planned in-service date is 4Q 2027, per Santee Cooper.
CPV Basin Ranch CPV Basin Ranch Energy Center TX 1,445 CC EIA status U; planned COD February 2029. Also present in the October 2026 ERCOT GIS report. EIA-860M Planned, September 2026, plant 69566; ERCOT Resource Adequacy / monthly GIS report landing page Construction is underway, per EIA. Watch later EIA and ERCOT GIS updates.
Golden Spread Electric Cooperative Elk Station TX 199.8 SC EIA status U; planned COD March 2027. EIA-860M Planned, September 2026, plant 58835 Construction is underway, per EIA. Watch for a later-stage or in-service update.
Arkansas Electric Cooperative Corporation Naples Power Plant TX 900 SC EIA status P; planned COD December 2028. EIA-860M Planned, September 2026, plant 68273 Watch TCEQ and later EIA status changes.
Fermi America Project Matador Gas Plant (PMG) TX 11,679.3 SC/CC EIA mixed P/T/U across a large multi-unit buildout. Planned CODs range from June 2027 to December 2030. EIA-860M Planned, September 2026, plant 69799 Large, phased campus. Watch later EIA-860M vintages and Texas air-permit updates for the next phases.
Virginia Electric and Power Company (Dominion Energy) Chesterfield VA 1,000 SC EIA status L; planned COD June 2029. EIA-860M Planned, September 2026, plant 3797 Watch Virginia SCC / company project updates and the November 24, 2026 EIA-860M file for status changes.
Invenergy / Red Oak Ridge Energy Center, LLC Red Oak Ridge Energy Center WI 1,210 SC EIA mixed L/P; planned COD December 2029. EIA-860M Planned, September 2026, plant 70453 Watch Wisconsin PSC filings and later EIA status changes.
Wisconsin Electric Power Company South Oak Creek WI 1,181.5 SC EIA status L; planned COD February 2028. EIA-860M Planned, September 2026, plant 4041 Watch Wisconsin PSC filings and later EIA status changes.
Black Hills Cheyenne Prairie Generating Station addition WY 120 SC EIA status P; planned COD December 2028. EIA-860M Planned, September 2026, plant 57703 Watch Wyoming siting / company updates and later EIA status changes.

* Canadys is a joint Santee Cooper / Dominion Energy plant. Santee Cooper states that 1,090 MW is its portion of the project. Public IRP materials describe a plant of about 2,180 MW.

Withdrawn or stale filings

EIA-860M can continue to show a plant after a siting case has been pulled. The row below is included so later editions can track a possible refile.

Developer / owner Project State Size (MW) Tech Status / stage Source What’s next
Western Minnesota Municipal Power Agency / Missouri River Energy Services Toronto Power Plant SD 145.2 SC WITHDRAWN. SD PUC granted withdrawal of the application without prejudice and closed EL25-028 on November 9, 2026. EIA-860M September 2026 still shows status L. SD PUC EL25-028 (docket closed November 9, 2026; order granting withdrawal without prejudice); EIA-860M Planned, September 2026, plant 69102 Watch for a possible refile at a new location. Do not treat the September 2026 EIA row as an active siting case.

Queue-only records (not yet confirmed in a permit or CPCN)

An interconnection request is an early signal, not proof that a plant will be built. Many ERCOT gas requests are still screening-level or are filed by project LLCs. The rows below were active in the October 2026 ERCOT GIS report. They have not been confirmed in this edition with an air permit, a CPCN, or an EIA planned-generator record. LCRA is a known public-power owner; that row is still flagged as a queue record until a permit or commission docket is confirmed.

Developer / owner Project State Size (MW) Tech Status / stage Source What’s next
Energy Forge One LLC Kilby1 Part 6 Large Block Combined Cycle TX 1,056 CC QUEUE ONLY. Active in the ERCOT interconnection queue. No IA date listed on the Interconnection.fyi project page. No air-permit or PUC confirmation in this edition. Interconnection.fyi, ERCOT 29INR0199; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Revisit when a permit, CPCN, or interconnection agreement appears.
Trailblazer Infrastructure LLC Trailblazer Natural Gas Generation Plant TX 1,026 Gas QUEUE ONLY. Active in the ERCOT interconnection queue. The project page does not specify simple-cycle vs combined-cycle. No air-permit or PUC confirmation in this edition. Proposed COD of December 2027 is aggressive if permits are not already in hand. Interconnection.fyi, ERCOT 27INR0575; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Triangulate with a permit or CPCN before treating it as a live build.
Liberty Data Center I, LLC Liberty Thermal Energy Center TX 1,400 Gas QUEUE ONLY. Active in the ERCOT interconnection queue. Long-dated proposed COD (July 1, 2032). No air-permit or PUC confirmation in this edition. Interconnection.fyi, ERCOT 33INR0006; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Confirm ownership, permits, and that the interconnecting entity would own and operate the generation.
Bullock Data Center, LLC Bullock Gas TX 1,400 Gas QUEUE ONLY. Active in the ERCOT interconnection queue. Long-dated proposed COD (July 1, 2032). No air-permit or PUC confirmation in this edition. Interconnection.fyi, ERCOT 33INR0005; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) Do not treat as construction-ready. Confirm ownership, permits, and that the interconnecting entity would own and operate the generation.
LCRA Sim Gideon Combined Cycle TX 880 CC QUEUE RECORD, known public-power owner. Active in the ERCOT interconnection queue. No separate CPCN or air-permit confirmation in this edition. Not listed in EIA-860M September 2026 Planned gas CT/CC. Interconnection.fyi, ERCOT 30INR0051; ERCOT Resource Adequacy / monthly GIS report landing page (October 2026 GIS report) A known owner, but still a queue record until a permit or CPCN is confirmed. Proposed COD December 15, 2030.

What this edition shows

  • Several mid-size simple-cycle projects are now in commission review or early construction planning, including Foundry Ridge in Wisconsin, Hub City in South Dakota, Peregrine in Idaho, and Mohave Energy Park in Arizona.
  • Combined-cycle additions tied to existing stations — Montour in Pennsylvania and Cooper Station in Kentucky — are moving through air permitting or public project planning, even though they are not yet in the September 2026 EIA planned file.
  • Private-grid and data-center-related generation is visible both in permitted form (GW Ranch in Pecos County, Texas) and in still-unconfirmed queue records in Hill County.
  • At least one otherwise well-documented mid-size municipal project, Toronto Power Plant in South Dakota, has had its siting application withdrawn. It remains in the September 2026 EIA file and should be watched for a refile, not treated as an active case.
  • The next EIA-860M release, on November 24, 2026, is the first place to look for status changes and for plants that have not yet appeared in the federal inventory.

If you are building a plant

HamidiTec works with end users and project owners — utilities, developers, cooperatives, EPCs, and the funds that directly back them — to source gas turbines and related power-generation equipment, direct from supplier. We do not publish an equipment list on this site.

If you have a project in permitting, procurement, or early engineering, send me your project and I will match it to equipment.

Compiled by HamidiTec LLC for the November 2026 Gas Project Tracker. Figures are taken from the public sources linked above and are current as of November 12, 2026 (America/New_York). This post will be revised as new EIA, commission, permit, and queue records are published.